View energy initiative

Back to initiatives

 

Improve national infrastructure of electricity transmission


Period
2015 - 2021

Implementing agencies
AFD

African partners
Other public body

Names of African partners involved
TANESCO

Donor involvement (incl. IOs)
Multi-donor, Multilaterals involved, Bilaterals involved

Names of donors involved (incl. IOs
AFD, EU

Geographical scope
Country

Countries where active
Tanzania

Sectors
Electricity, Energy Efficiency

Sub Sectors (Electricity)
Electricity system

Type of intervention
Operative program / delivery mechanism (downstream)

Type of technical assistance
Policy support / institution building, Project preparation / implementation, Skill development / training

Gender focus
No

Climate focus
No

Type of financing
Debt

Main objectives
The objective is to improve the access to electricity for the population; reduce technical losses and underserved electricity demands; reduce greenhouse gas emissions by increasing the energy efficiency of the network

Main activities
The project consists in three phases: 1) the rehabilitation of 10 electricity substations in the provinces of: Mlandizi, Chalinze, Same, Mufundi, Mbeya, Dodoma, Mwanza, Musoma, Bukoba et Tabora; 2) rehabilitation and extension of the communication network using optical fibre cables and improvement of wide area network guidance with new softwares; 3) reinforcing TANESCO capabilities with backing the handover and markets follow-up in the achievement of environmental impacts analysis and the management of electrotechnical equipment stocks.

Comments

Sources
https://www.afd.fr/fr/ameliorer-les-infrastructures-nationales-de-transmission-delectricite

Contact information
Emmanuel Baudran, Office Director, afddaressalaam@afd.fr